Centipod WEC, Advanced Controls, Baseline LCOE
Project baseline levelized cost of energy (LCOE) model for the Centipod WEC containing annual energy production (AEP) data, a cost breakdown structure (CBS), model documentation, and the LCOE content model. This baseline was built for comparison with the resultant LCOE model, built after implementation of the model predictive control (MPC) controller.
Complete Metadata
| bureauCode |
[ "019:20" ] |
|---|---|
| dataQuality | true |
| DOI | 10.15473/1493766 |
| identifier | https://data.openei.org/submissions/7774 |
| issued | 2016-02-15T07:00:00Z |
| landingPage | https://mhkdr.openei.org/submissions/70 |
| programCode |
[ "019:009" ] |
| projectLead | Tim Ramsey |
| projectNumber | EE0006404 |
| projectTitle | Advanced Controls for the Multi-pod Centipod WEC device |
| spatial | {"type":"Polygon","coordinates":[[[-180,-83],[180,-83],[180,83],[-180,83],[-180,-83]]]} |